Admin's other articles

4349 The World without Bankruptcy Laws

Bankruptcy is one of the natural states which a company may find itself in. Entrepreneurship is primarily about taking risks. When companies take risks, some of them succeed, whereas others fail. Hence failure is a natural part of the business. However, many critics of bankruptcy laws believe that there isn’t a need for an elaborate […]

4348 The Wirecard and Infosys Scandals are a Lesson on How NOT to Treat Whistleblowers

What is the Wirecard Scandal all about and Why it is a Wakeup Call for Whistleblowers Anyone who has been following financial and business news over the last couple of years would have heard about Wirecard, the embattled German payments firm that had to file for bankruptcy after serious and humungous frauds were uncovered leading […]

4347 Why the Digital Age Demands Decision Makers to be Like Elite Marines and Zen Monks

How Modern Decision Makers Have to Confront Present Shock and Information Overload We live in times when Information Overload is getting the better of cognitive abilities to absorb and process the needed data and information to make informed decisions. In addition, the Digital Age has also engendered the Present Shock of Virality and Instant Gratification […]

4346 Why Indian Firms Must Strive for Strategic Autonomy in Their Geoeconomic Strategies

Geopolitics, Economics, and Geoeconomics In the evolving global trading and economic system, firms and corporates are impacted as much by the economic policies of nations as they are by the geopolitical and foreign policies. In other words, any global firm wishing to do business in the international sphere has to be cognizant of both the […]

4345 Why Government Should Not Invest Public Money in Sports Stadiums Used by Professional Franchises

In the previous article, we have already come across some of the reasons why the government should not encourage funding of stadiums that are to be used by private franchises. We have already seen that the entire mechanism of government funding ends up being a regressive tax on the citizens of a particular city who […]

See More Article from Admin

It is a long established fact that a reader will be distracted by the readable content of a page when looking at its layout.

Visit Us

Our Partners

Search with tags

  • No tags available.

Introduction

This article details the high level project plan and the components of the same. A project is a success if it meets the objectives of time, cost, technical and business. Project objectives are defined in the preliminary project scope statement. As mentioned above, a project is deemed complete if the project objectives have been met. The objectives should be clear and achievable.

Project Objectives

The objectives for this project have been summarized as:

  1. Time

    The project plan must contain the time taken to complete the project end-end from requirements to implementation. A detailed analysis of each stage and the time taken for the same must be outlined upfront and milestones for each stage defined.

  2. Cost

    The cost for completion of the project as defined by the time taken to complete and the technical and business objectives being met is to be defined. All the project objectives are linked to each other and any change in one variable affects the others as well. For e.g. a change in the technical requirements would mean that more time would be required to complete the project and this in turn affects the cost. Thus there are cascading affects on each of the variables.

  3. Business

    The business objectives have to be clearly spelt out by your company in terms of the sales generated, the cost benefit analysis of building a website and consequent revenue generation etc.

  4. Technical

    The technical requirements can be stated in terms of the quality of the deliverables and the number of defects found during each of the testing phases and the turnaround time for implementation etc.

Work Breakdown Structure

The above chart is a representation of the Work Breakdown Structure (WBS) for the project. It represents a high to medium level summary and it can be refined further. The WBS has been summarized in the organization chart keeping in mind some factors like:

  • The WBS is a high level overview that can be broken down into smaller and smaller package of work until the Project Manager achieves the level of granularity that he/she wants. This granularity is to be obtained keeping in mind the realistic scenarios. For e.g. the first level of the WBS described above is the same as the project life cycle, Requirements, Design etc.

  • The next levels of the WBS are broken down based on the work packages that are to be assigned to the team members. The packages must be designed in such a way that the deliverables are met.

  • In a way, the WBS is the foundation of the project. The time and cost of the project are defined in terms of the work packages and estimated accordingly.

Responsibility Matrix

ActivityTeam Member
Team member 1Team member 2Team member 3
A (design)P S
B (coding) SP
C (testing)SP 

P - Primary responsibility

S - Secondary responsibility

This chart cross references the WBS created for the project. Each of the work packages created in the WBS is allocated to each of the team members with primary and secondary responsibilities assigned accordingly.

Project Plan

The project plan consists of the above details as well as the WBS and the responsibility matrix. A detailed project plan needs more elaboration and is a separate activity altogether.

Article Written by

Admin

Leave a reply

Your email address will not be published. Required fields are marked *

Related Posts

Why are Companies Constantly Upgrading their ERP Systems?

Admin

It’s Now or Never: Why Business Must Embrace Sustainability before it is Too Late

Admin

The Pharma Sector and Intellectual Property Rights: Pros and Cons

Admin